Delivering High-Strength, Regulated Structural Infrastructure for Nigeria’s Utility and Electrification Networks.
Established in 2017, SSK Integrated Services Limited combines cutting-edge technical expertise with rigid quality management systems to provide turnkey electrical infrastructure and civil engineering services. We build quality into our raw materials, casting methodologies, and rigorous validation tests to consistently exceed industry and regulatory requirements.
Our Services
Need Any
Consultation?
Civil Engineering Laboratory Analysis,Testing and Services
SERVICE OVERVIEW:
Commercial independent testing and quality control validation conducted within our ultra-modern, on-site engineering laboratory.
THE TECHNICAL EDGE:
- Custom Testing Rig:
Our facility features a custom performance validation rig and dynamometer to simulate high-load, real-world environmental stress through rigorous type and proof tests (deflection and destructive testing).
- Material Quality Control:
On-site laboratory analysis guarantees total defect detection and quality monitoring of all input materials before production begins.
- Reference Standards Compliance:
We benchmark all material tests against strict Nigerian Industrial Standards, including:
- NIS 586:2020 (Reinforced and Prestressed Concrete Poles)
- NIS 117:2010 & NIS 746:2012 (Reinforcement & Granite Chippings Quality)
- NIS 444-1:2018 & NIS ISO 1920 (Cement Composition & Concrete Tests)
- NIS 554:2007 (Industrial Water Quality)
A showcase of a few of our high-voltage and low-voltage concrete pole supply contracts
Project Title: SSAGS–CEIP Ogbotobo Transmission Node Project
Contractor: PIMO
Deployment: 50 Nos of 10.36m Reinforced Concrete Poles
Timeline: Completed – August 2021
Engineering Milestone: Cube strength of 44.44 N/mm² at 28 days.
Project Title: SSAGS–CEIP Tunu Node Transmission Project
Contractor: Westfield
Deployment: 173 Nos of 10.36m Reinforced Concrete Poles
Timeline: Completed – December 2021
Engineering Milestone: Compressive cube strength achieved @ 28 day 46.52 N/mm²
Project Title: CEIP – Otumara Section Two (Ugborodo Community Network)
Contractor: Tadoro Nigeria
Deployment:5 Nos of 12.2m Poles and 83 Nos of 10.36m Reinforced Concrete Poles
Timeline: Completed – August 2024
Engineering Milestone: Strength achieved 43.22 N/mm² @ 28 day
Project Title: CEIP – Escravos Infrastructure Project (Phase I)
Contractor: Realhatt Venture
Deployment: 4 Nos of 12.2m Poles and 227 Nos of 10.36m Reinforced Concrete Poles
Timeline: Completed – July 2024
Engineering Milestone: Strength achieved 41.48 N/mm² @ 28 day
Project Title: CEIP – Escravos Infrastructure Project (Phase II)
Contractor: Tarimore
Deployment: 4 Nos of 12.2m Poles and 498 Nos of 10.36m Reinforced Concrete Poles
Timeline: Completed – July 2024
Engineering Milestone: Strength achieved 43.22 N/mm² @ 28 day
Project Title: SSAGS–CEIP Iduwini Cluster Town Network
Contractor: S2 Generation Services
Deployment: 55Nos of 8.53m Reinforced Concrete Poles
Timeline: Completed – January 2025
Engineering Milestone: Cube strength achieved 44.44 N/mm² @ 28 day
Project Title: SSAGS–CEIP Ogbotobo Transmission Node Project (Expansion I)
Contractor: PIMOMAFUTA
Deployment:350Nos of 10.36m Reinforced Concrete Poles
Timeline: Completed – August 2025
Engineering Milestone: Strength achieved 43.22 N/mm² @ 28 day
Project Title: FYI-SOUTH BANK
Contractor: Renaissance Africa Energy Company Limited (RAEC)
Deployment: 80nos 12.2m Concrete Pole
Timeline: Completed – August 2025
Engineering Milestone: Strength achieved 47N/mm² @ 28 day
Project Title: SSAGS–CEIP Ogbotobo Transmission Node Project (Expansion II)
Contractor: MOPROJECT
Deployment: 1000 Nos of 8.53m Reinforced Concrete Poles
Timeline: Completed – December 2025
Engineering Milestone: Strength achieved 43.22 N/mm² @ 28 day